This contract consists of three projects constructed simultaneously on the Route 29 Corridor: construction of a grade separated intersection on Route 29 with major utility relocations, accelerated bridge and roadway construction; 2.9 mile long widening of Route 29; and 2.9 mile construction of Berkmar Drive (new road) and bridge paralleling Route 29.
CES Consulting LLC(CES) was responsible for providing the Quality Assurance Program for this project. CES Consulting provided the Quality Assurance Manager, QA senior Inspectors, QA testing technician and office support staff.
Grade separated intersection at the Route 29 and Rio Road.
Major utility relocations prior to construction of roadway and bridge
Accelerated bridge construction (bridge has to be completed in 103 days when turn movements are restricted on Route 29) using precast box beams, tie-back walls and other innovative ideas.
2.9 miles of roadway construction (including drainage, utilities, traffic signals, etc.) widening of Route 29
Construction of parallel road (Berkmar Drive) to Route 29. Work includes construction of new bridge crossing over Rivanna River with drilled shafts and major earthwork operations.
Extensive environmental permitting and mitigation prior to construction work starting
Extensive public outreach to business on Route 29 Corridor as well as local county boards, City of Charlottesville, local residents and travelling public
Ensure all projects are constructed according to VDOT Design Build Specifications and Guidelines
Full time Quality Assurance Manager responsible for execution of QA plan for duration of project
Ensure and responsible for implementation of Lane Corman’s approved QC/QA program
Provide qualified and certified inspection and testing staff to inspect all work operations
Provide experienced office staff to ensure that all work is properly documented and tracked
Assist Design Build Contractor to mitigate construction quality issues, resolve NCRs, work with QC manager and VDOT to ensure quality in all construction operations
Tracking and testing of all materials per VDOT Design Build guidelines for QA & QC
Approval of all materials used on project per VDOT Materials Section processes/procedures
Ensure progress photographs and daily reports are consistent
Compile and responsible for all project records pertaining to Quality Assurance
Owner: VDOT
Cost: $116.75 Million
Project Dates: Feb 2015 to October 2017