This parking lot is built at the intersection of Route 234 By pass and I-66 on Cushing Road giving access to I-66 east bound lane and accommodates over 420 parking spaces.
This project included grading, drainage, underdrains, guardrail, asphalt pavement, signs,lighting,communication equipment, signalized intersection, pavement markings, planting/ and concrete items. The concrete comprised of items such as curb and gutter, light pole foundations,concrete pads, concrete sidewalks,bus shelter,bicycle racks and concrete end walls.
CES Consulting LLC(CES) performed pre-construction and inspection services for project. CES provided a scheduler and an inspector for staffing.
PRE-CONSTRUCTION: CES provided preliminary engineering services, i.e., constructability and bidability reviews, Contract Time Determination Report (CTDR) and contract special provisions.
CONSTRUCTION: CES performed inspection services in the field. CES project inspector’s responsibilities included:
Ensuring that all work was per VDOT standards and specifications
Ensuring that all testing was performed at the correct frequency
Measuring and documenting daily work pay items
Testing concrete to ensure air, temperature and slump requirements were met and work was within specification requirements
Inspecting lighting items, signal items and various other items
Other support,i.e., project controls,monthly schedule updates,and change order estimates
Working closely with the contractor to ensure all field design and utility conflicts were resolved at the lowest level possible
Grading
Drainage and underdrain installations
Guardrail Installations
Lime stabilization and manipulation
Lighting and signalized intersection
Bus shelter installations
Landscaping/planting
Asphalt pavement construction and reconstruction
Concrete items such a scurb and gutter,sidewalk, signal pole foundations and ADA ramps
Bicycle racks
Owner: VDOT
Cost: $5.3 Million
Project Dates: June 2012 to July 2013
© 2016 All Rights Reserved CES CONSULTING LLC